From Bid Tariff to Daily Dispatch — One Platform

Flagship — Bid-Stage Sizing · Now Live

RTC-X Sizing &
Simulation Platform

RTC-X takes your RE profiles, BESS specifications, and PPA terms, stress-tests them across thousands of dispatch solves and a Monte Carlo resource-risk simulation, and returns the bid tariff you take to the tender. Live today — built on team experience sizing 10+ utility-scale FDRE and RTC bids.

Advisory Services ↓
10+*
Utility-Scale Bids Sized
*team experience — FDRE & RTC tenders
93.8%
Revenue Capture
vs perfect hindsight
18+
Months Backtested
real IEX data
Zero
OEM Violations
constraints in the formulation
Daily
Automated Dispatch
before DAM deadline

Revenue capture, backtest and dispatch figures are PRISM engine results on IEX data. The bids-sized figure reflects team experience.

RTC-Xsizes the bidMESH-Tplaces the portfolioSHIELDprotects the contractPRISMruns the dispatchand COMPASS structures C&I supply

Flagship Product

RTC-X Sizing & Simulation PlatformNOW LIVE

Every FDRE bid comes down to one number — the tariff. RTC-X works backwards from your target equity IRR, stress-tests it across thousands of dispatch solves and a Monte Carlo resource-risk simulation, and delivers the bankable bid tariff you commit to.

The stakes are not abstract. A 250 MW round-the-clock supply settles roughly 1.8 TWh a year, so every 10 paise on the tariff is worth about ₹18 crore a year — for the life of the PPA, with no second chance after submission. Bid too high and the tender is lost; bid too low and equity returns erode for 25 years. A single-scenario spreadsheet assumes one future, keeps Year 1 battery performance for 25 years, and locks in an RE-to-BESS ratio that cannot be undone once the bid is won. Each of these risks is quantifiable before submission — that is what RTC-X is for.

The model behind RTC-X has sized more than 10 utility-scale FDRE and RTC bids.* *team experience

15-min dispatch · all 35,040 blocks/yearValidated 99.7%+ vs independent reference model25-yr lender-grade financials — P&L, DSCR, balance sheetInvestment report & diligence workbook exportsTender presets: SECI, NTPC RTC, SJVN FDRE, state DISCOMEvery report re-verifies its own numbers on an independent path
PRE-BIDRTC-X delivers the bid tariffPOST-CODPRISM operates it

FDRE / RTC Sizing

Optimal RE-to-BESS ratios, storage duration, and connectivity-to-capacity mapping, solved as a non-linear equity IRR maximization across the project life. Technology-agnostic: lithium-ion, flow batteries, pumped hydro, and emerging chemistries, each with its own cost trajectory.

BESS Placement Decision

Where to place storage across your portfolio for maximum contractual compliance and merchant upside. Site-specific ambient, grid, and curtailment inputs.

Augmentation Strategy

When to augment, how much, and which chemistry — modeled against degradation trajectories, warranty thresholds, and revenue trade-offs over the project life.

Resource Risk — Monte Carlo

Monte Carlo simulation over historical resource years delivers the full EIRR distribution and the minimum-DSCR distribution — a P50 and P90 you can defend, with debt-shortfall scenarios flagged before you commit to the tariff.

Output: Bankable bid tariff backed by P50/P90 revenue projections, optimal storage duration curves, augmentation timing, and full sensitivity analysis on degradation and price assumptions — lender-ready from day one.

Inside the platform

RTC-X is built for bid committees that want to interrogate the answer. The solution space is visible, the alternatives are priced, and the risk sits on the table.

See the whole solution space

Every evaluated sizing is a point in a 3D cloud, and the EIRR surface over wind and BESS shows the peak is global, not local — you can see it for yourself. Visuals, not just a number to trust.

Top 15 solutions, confirmed. The best configurations, each re-confirmed on the full 25-year model.

Alternatives priced. Lowest-wind, lowest-BESS and lowest-solar variants stay on the table, tariffs attached.

Trade-off explorer. Every feasible candidate on one interactive view, ready for what-if questions.

Every evaluated sizing, the optimum ringed

The EIRR surface over wind × BESS

Weigh the risk, then narrow it

Risk and return, side by side. The four leading sizings carry EIRR distributions next to their tariffs.

Downside protection. P50 is the pitch; P90 is the lender's floor; debt-shortfall scenarios flagged.

Strategies that narrow the risk. More storage, less wind, a different split — each move priced on the tariff.

Compliance, year by year. Commitment coverage shown through time, the handover to augmentation explicit.

Model the real project

Multi-plant, multi-generator. Shared evacuation and site-specific resource, sized together in one optimization.

Tender connectivity built in. Non-solar-hour access and other real tender structures modeled as constraints.

A 25-year IEX price view. Elaris's own DAM price path from a supply-stack simulation, haircut option included.

True co-optimization. Dispatch physics and project finance solve together, never in sequence.

From tender document to bid number

A configured tender runs in hours. A first bid — data collection, sizing and simulation, a sensitivity review with a go or no-go recommendation, and the final bid package — typically takes 2 to 4 weeks end to end.

01
Define the construct
Tender name, demand window, tariff scope, penalties — explicit, nothing hidden.
02
Configure the plant
Multi-plant topology, shared evacuation, C-rate-aware BESS, your resource data.
03
Optimize & stress
Sizing search with capability floors, 25-year projection, Monte Carlo risk.
04
Take the number to the bid
Investment report, lender workbook, audit trail.

Between bids — for BD and strategy teams

The bid is not the only decision RTC-X supports. At least two new tender constructs are modeled and released as presets every quarter, as SECI, NTPC, SJVN and the state DISCOMs announce them — so for business development and strategy teams, the subscription is continuous decision intelligence rather than a tool that comes out at bid time.

Understand the construct
Each preset is a working model of the tender — demand window, penalty mechanics, settlement logic — and running it makes plain which levers actually move the tariff.
Quantify a position
Change a clause and re-run: what a revised demand profile, penalty rate or minimum supply requirement does to the tariff and the equity IRR comes back as a number, so responses to draft tenders and policy consultations carry evidence.
Cover the whole market
Presets arrive as tenders are announced, including constructs you may never bid, so the team sees how each new construct behaves before deciding where to compete.

Flagship Product

PRISM Hybrid Optimization EngineNOW LIVE

Winning the tender is the easy part. In operations, revenue leaks daily — blocks scheduled at the wrong price, storage cycled when the spread doesn't justify the degradation, PPA shortfalls that turn into penalties. PRISM closes that gap: a dispatch optimizer for solar + wind + BESS assets that maximizes revenue while meeting PPA commitments, with the OEM warranty envelope enforced as hard constraints.

96-block D+1 schedule + 48-block D+2 look-ahead93.8% revenue capture vs perfect hindsight91% charging cost capture vs a greedy baselineZero OEM envelope violations — constraints in the formulation

Price Intelligence

96-block DAM forecasts with confidence bands. RTM spike flags. Market selection per block. Delivered before the DAM deadline, every day.

Hybrid Optimizer

Co-optimizes solar + wind + BESS as one system. PPA obligations as hard constraints. Merchant upside in remaining capacity. Intraday re-dispatch.

Battery Digital Twin

OEM warranty envelope mathematically enforced — SoC, C-rates, thermal limits, degradation. The optimizer cannot violate these constraints.

Risk Modes

Three operating modes: Conservative, Moderate, Aggressive. A ₹50K arbitrage that costs ₹2L in degradation gets skipped automatically.

Configurable for every asset: Solar + Wind + BESS, Solar + BESS, or Standalone BESS. PPA with merchant upside, PPA only, or merchant only. PPA preference or merchant preference dispatch.

Start with a 30-day discovery pilot

PRISM runs on your asset's historical data for a fixed fee, and the pilot ends with predicted versus actual dispatch, the revenue capture rate, and the revenue delta in rupees. No integration is needed to begin — schedules arrive as Excel workbooks your operations team can act on the same day, with nothing new inside your network. API and EMS integration come later, once the value is proven. The license decision comes after the numbers.

What your operations team gets

Daily, automated
The 96-block day-ahead schedule with a 48-block look-ahead for the following day, market selection per block, and charging windows — delivered before the DAM deadline, every day.
Intraday, continuous
Re-optimization as generation and prices move, live SoC and thermal tracking, and price spike alerts when RTM blocks turn valuable.
Reporting & integration
A web dashboard, historical analytics, and a monthly performance report. API and SCADA or EMS integration when your team is ready for it.

Deployment path

Shadow mode means PRISM runs alongside your current operations before anything switches over — you compare its schedules against yours with real numbers, at zero operational risk.

01
Weeks 1–2 · Calibration
Battery specifications, solar and wind profiles, grid connection limits, and the thermal model.
02
Week 3 · First schedules
Delivery starts in Excel — no SCADA work, nothing new inside your network.
03
Week 4 · Shadow mode
PRISM runs alongside your current dispatch. You compare, block by block.
04
Week 5+ · Go live
Automated daily optimization with rolling intraday corrections.

Flagship Product

SHIELD Contract Risk IntelligenceEARLY ACCESS

Am I signing a bad BESS contract? SHIELD answers the questions your legal team can't — because they're technical, not legal.

?Where is OEM risk transfer incomplete?
?Which terms are outside market standard?
?Where am I exposed on throughput, augmentation, warranty, and interface scope?
85+
Risk Parameters
16
Quality Gates
21
Cert. Checks
25
Acceptance Tests
6
LD Risk Areas

Availability Risk Exposure

97% availability sounds standard — until you read the fine print. How is it calculated? Are planned outages excluded? Is it measured at the container, system, or POI level? Does the LTSA tie availability guarantees to O&M fee escalation — or does coverage weaken as the asset ages? A 3% gap in definition can mean weeks of uncompensated downtime.

SAT — Are You Testing What Matters?

Are you measuring usable energy at the BESS meter or at the DC terminal? Is RTE measured AC-AC or DC-DC? Is power tested at 51°C ambient or lab conditions? Does your SAT cover fire suppression system activation, FACP response, and chiller performance under peak ambient — or just the battery? The wrong measurement point or missing test can lock in years of underperformance you can't claim against.

FAT — Evidence, Not Declarations

Repairing at site is a mess — logistically, commercially, and contractually. FAT is where you catch defects before they become site-level problems: DCIR variance, capacity shortfalls, cell age, thermal non-uniformity, BMS communication faults, and chiller/FACP integration gaps. And vendor declarations are not bankable — lot-wise capacity and DCIR distributions as raw data, batch traceability from cell to container, and cell-age limits at dispatch are. Evidence packages belong at FAT, not at warranty-claim time.

Warranty Enforceability & the PBG Cliff

A 20-year warranty on the cover page is a commercial wrapper — what matters is whether it pays out. What backs your recourse when the performance bank guarantee steps down? On many contracts, post-year-five recovery collapses to the annual LTSA fee — a fraction of the exposure. Does dispatch variation void the warranty, or is throughput flexibility locked to an agreed SOC, DoD, C-rate, and temperature envelope? If the OEM discontinues the cell line, is there an equivalence clause — or does the warranty hollow out with it? SHIELD maps enforceability year by year against your actual exposure.

Cell, Thermal & Fire Safety Gaps

High DCIR means faster degradation and thermal runaway risk. High cell-to-cell variance means your weakest cell limits the entire rack. But beyond cell quality — does your contract specify fire safety scope clearly? UL 9540A testing, NFPA 855 compliance, deflagration venting, and gas detection obligations are often assumed but not contractually assigned. SHIELD identifies where quality and safety thresholds are missing, too loose, or ambiguously scoped.

LDs, Exclusions & Interface Scope

Are your liquidated damages actually protective — or just decorative? SHIELD stress-tests your LD structure across 6 categories and identifies where caps are too low, where remedies don't bite, and where carve-outs quietly void the guarantees you thought you had. It also maps the interface scope: where does the OEM's obligation end and yours begin? In multi-vendor builds, ambiguity at the BMS–PCS–EMS boundaries is the most common cause of grid-connection delay — and where most post-COD disputes originate.

Commercial and technical risk intelligence for energy contracts. Beyond benchmarking, SHIELD identifies where risk transfer is incomplete, where you are exposed, and what best-in-class terms look like globally — clause by clause, against how your asset will actually operate.

In Development

MESH-T Portfolio IRR OptimizerIN DEVELOPMENT

A portfolio is more than the sum of its plants. RTC-X sizes one bid; MESH-T decides where the assets go across many — placement, connectivity allocation, and build phasing solved as one multi-plant optimization, with portfolio equity IRR as the objective.

Most portfolios are assembled plant by plant, each site judged on its own CUF and capex. MESH-T reruns that logic at portfolio level, where shared evacuation, congestion, and phasing change the answer — often completely.

Portfolio IRR Optimization

The objective is the portfolio's equity IRR, not a ranking of individual sites. Plants interact — through shared evacuation, connectivity limits, and phasing — and MESH-T solves them together in one optimization.

Connectivity & Evacuation Allocation

Which capacity goes to which substation, and what congestion and curtailment will cost there. Capex against evacuation trade-offs made explicit, before the connectivity applications are filed.

Asset Placement

Solar, wind, and storage placed against resource quality, connectivity, and tariff together. The best wind site is not always the best project, and the difference is quantifiable.

Phasing & Capex Trade-offs

Build order across the portfolio, modeled against falling BESS prices and evacuation availability. Includes battery value under constrained evacuation, where storage earns its place by shifting rather than adding energy.

What you can do today. Portfolio placement and connectivity studies are available now as a scoped advisory engagement, with results in 2 to 3 weeks. MESH-T is the platform being built to run that optimization as a product.

Flagship Product

COMPASS C&I Sizing & Tariff EngineNOW LIVE

Sizing and tariff analysis for C&I supply — a two-sided optimization. On one side, the generator's solar + wind + BESS mix; on the other, the consumers it serves, each with its own load profile. COMPASS holds the generator's equity IRR at target and solves the mix, the consumer allocation, and the tariff for maximum savings on every load profile.

A worked example: one solar + wind + BESS portfolio serving three consumers — a two-shift manufacturer, a round-the-clock data facility, and a day-peaking commercial load. COMPASS holds the generator at its target IRR and returns a single tariff and an allocation that clears each consumer's savings threshold. Sized from either side alone, the same portfolio leaves value on the table for both.

Back-tested against real DISCOM open-access bills — to the paisaState packs: Maharashtra, Tamil Nadu, Karnataka, Gujarat — sources citedToD-slot banking ledger inside the optimizationCustomer-safe proposal PDF, internal memo, and lender workbook
PRE-CONTRACTCOMPASS delivers the sizing & tariffPOST-CONTRACTsavings tracked against DISCOM baseline

RE Mix & Sizing

Optimal solar, wind, and BESS combination for the load being served — one facility or a portfolio of consumers on 15-minute profiles. Contract demand, ToD structure, and seasonal shape modeled per consumer; the mix is solved against the aggregate.

Structure & Interconnection

Third-party open access and group captive compared across interconnection routes from 33 kV DISCOM-connected to 220 kV ISTS — with the full state charge and loss cascade priced for each: transmission, wheeling, CSS, additional surcharge, standby, and electricity duty.

Tariff & Savings

Landed cost per unit computed against each consumer's DISCOM bill, including ToD arbitrage and demand charge impact. Outputs the PPA tariff that holds the generator's IRR while maximizing annual savings for every consumer served.

Regulatory Sensitivity

Savings tested across surcharge revisions, banking restrictions, grid tariff escalation, and load growth assumptions. Results delivered as P50/P90 bands, not a single-point estimate.

Output: Recommended capacity mix, consumer allocation, procurement structure, and target PPA tariff — with P50/P90 savings projections and sensitivity analysis on regulatory and load assumptions. A C&I PPA runs 15–20 years; the sizing decision deserves the same rigor as the contract.

Why Elaris

Operating Experience, Built Into Software

Grounded in Plant Data

Team experience includes commissioning multiple utility-scale BESS projects across India. Every constraint in the model comes from observed plant behaviour.

IEX Native

Trained on 18+ months of real IEX DAM and RTM data. Indian calendar awareness — Republic Day, Diwali, monsoon surplus, summer peaks — baked in.

Warranty as a Hard Constraint

The OEM operating envelope is mathematically enforced inside the formulation, so the optimizer cannot produce a violating schedule.

PPA First, Then Merchant

Contractual obligations are met first, and merchant upside fills the remaining capacity. Lenders see compliant dispatch; investors see protected returns.

Case Studies

The Delta We Deliver

Anonymized decisions from team experience, and the numbers that drove them.

PRISM
87%
In-House
92%
PRISM

Dispatch Optimization — Merchant BESS

Physics-unaware dispatch was degrading the battery faster than the revenue justified. PRISM captures more and degrades less — automated before the DAM deadline, every day.

RTC-X
24%
High Variance
22%
Bankable

100 MW FDRE — Sizing Evolution

A wind-heavy mix hit 24% P50 EIRR with a wide P50–P90 spread; as BESS prices fell, a solar + storage mix gave up 2pp for dramatically less variance. Lenders price variance ahead of the best case.

ADVISORY
Staggered
Client's Model
Right-Sized
IRR-Accretive

BESS Augmentation — DC vs AC Coupling

The client's model staggered augmentations across several years. One right-sized augmentation, with the preferred coupling, was the IRR-accretive answer.

RTC-X
12%
Best Case EIRR
!
No-Go
Recommendation

RTC Bid — Go/No-Go Decision

The Monte Carlo EIRR distribution ran from 3% to 12% — even the best case fell short of the equity hurdle. Sometimes the best bid advisory is not to bid.

ADVISORY
CUF
Typical Ranking
IRR
Actual Ranking

Wind Asset Distribution — Multi-Site

The client ranked wind sites by CUF. Ranked by project-level IRR — connectivity, evacuation and tariff included — the order flipped entirely.

ADVISORY
Months
Decision Delayed
Quantified
IRR Delta

BESS Placement — Solar vs Wind Co-location

Solar co-location meant predictable DAM capture; wind meant better RTM spreads. The quantified IRR delta settled in one number what intuition had debated for months.

SHIELD
Yr 3
PBG Steps Down
Yr 6
Risk Surfaces

BESS Contract — The PBG Cliff

Physics models showed underperformance surfacing from year six — after the performance bank guarantee had already stepped down in year three. The PBG schedule was restructured before signature.

COMPASS
IRR
Generator · Fixed
+
Savings
Consumers · Maximized

C&I Supply — Two-Sided Optimization

COMPASS holds the generator's equity IRR at target while the RE mix and consumer allocation maximize savings on every load profile — the solar, wind and BESS proportions tabulated against each consumer's share. One-sided sizing leaves money on the table for both.

Software Plans

Plans & Pricing

Monthly rates, billed quarterly. Annual billing: two months free.

RTC-X

A project is one tender workspace, active in a calendar month. Every plan includes the full engine — block-level dispatch, the sizing optimizer, 25-year project finance and exports — and every new tender preset as it is released, at least two a quarter.

Basic
₹2,00,000₹1,20,000 / month + GST · billed quarterly
40% launch discount · till Oct 2026
  • 2 active projects / month
  • 15 full model runs per project
  • Investment report & diligence workbook exports
  • 2-hour onboarding training included
  • Top-ups: ₹60,000 per project
Enterprise
₹3,00,000₹1,80,000 / month + GST · billed quarterly
40% launch discount · till Oct 2026
  • Everything in Basic
  • 5 active projects / month
  • 25 full model runs per project
  • 10 hours of bid assistance / month
  • Top-ups: ₹25,000 per project

PRISM

Priced per asset under optimization. Every plan includes the battery digital twin and dispatch schedules delivered before the DAM deadline, daily. New assets can start with a 30-day discovery pilot on historical data — fixed fee, predicted versus actual, and the revenue delta in rupees.

Basic
₹2,40,000₹1,44,000 / month + GST · billed quarterly
40% launch discount · till Oct 2026
  • 1 asset under optimization
  • Daily DAM/RTM dispatch schedules
  • Risk modes: Conservative / Moderate / Aggressive
  • Monthly performance report
  • Onboarding & model calibration included
Enterprise
₹3,60,000₹2,16,000 / month + GST · billed quarterly
40% launch discount · till Oct 2026
  • Everything in Basic
  • Up to 3 assets under optimization
  • Intraday re-dispatch & RTM spike alerts
  • Quarterly model recalibration
  • Dedicated support

COMPASS

A study is one supply structure analyzed end-to-end — RE mix sizing, consumer allocation, open-access vs group-captive comparison, and tariff with P50/P90 savings bands. Up to 3 consumer load profiles per study; larger portfolios scoped on request.

Basic
₹1,00,000₹60,000 / month + GST · billed quarterly
40% launch discount · till Oct 2026
  • 1 study / month
  • RE mix sizing, allocation & structure comparison
  • Savings report with P50/P90 bands
  • Regulatory sensitivity analysis
  • Top-ups: ₹30,000 per study
Enterprise
₹1,50,000₹90,000 / month + GST · billed quarterly
40% launch discount · till Oct 2026
  • Everything in Basic
  • 3 studies / month
  • Multi-site portfolio comparison
  • Procurement support hours
  • Top-ups: ₹20,000 per study

SHIELD reviews and MESH-T portfolio studies are scoped to the mandate — write to info@elarispower.com for a proposal.

Discounted rates apply to subscriptions started before October 2026; standard rates apply thereafter. Custom run limits and dedicated single-tenant deployments on request — write to info@elarispower.com.

Trust & Security

Built for bid rooms that handle confidential numbers

Data stays in India
Hosted and backed up in-country (Chennai region) — never leaves Indian jurisdiction.
Per-organization isolation
Your tenders, costs and results are invisible to every other customer — enforced in the data layer, audit-logged.
Encrypted & recoverable
AES-256-encrypted nightly backups with off-site copy; restore procedure drill-tested.
Engineering you can audit
Dispatch engine validated 99.7%+ against an independent reference model; every change gated by an automated test suite.

Security & data-practices document for procurement review — .

Deep Domain Expertise

Advisory Services

Team experience includes commissioning multiple utility-scale BESS projects across India. The advisory practice draws directly on that operating record.

Multiple
Utility-Scale BESS Projects Commissioned
Multi-GW
FDRE Capacity Modeled
Billions $
Project Capex Supported
18%+
Equity IRR Delivered
All Tier 1
OEMs Evaluated

FDRE & RTC Bid Optimization

Hands-on bid advisory powered by our RTC-X platform. Non-linear equity IRR maximization, connectivity-to-capacity mapping, and degradation-adjusted dispatch modeling. Team experience spans multi-GW FDRE portfolios and billions of dollars in project capex, delivering 18%+ equity IRRs.

RfP & Vendor Selection

RfP specifications designed around how your BESS will actually operate, with a contractual terms framework benchmarked against global comparatives. Bid evaluation weighs warranty evidence alongside the warranty curve, because an evaluation that treats every vendor curve as enforceable rewards the most aggressive claim.

Vendor & Contract Due Diligence

Independent due diligence across all Tier 1 BESS OEMs. Identification and negotiation of high-risk contractual clauses: warranty carve-outs, sampling rate loopholes, certification ambiguities, liquidated damages gaps. Includes cell-format bankability — emerging high-capacity formats trade real capex savings against thin field data, and the wrapper risk moves with them.

EMS & Controls Strategy

Independent EMS platform evaluation, DSM controller logic specification, and SCADA integration oversight. Independent benchmarking against the strongest platforms in the market.

Power Market Strategy

IEX DAM/RTM optimization, DSM controller logic specification, scheduling strategy, and merchant revenue modeling for operating assets. Built on observed IEX market data.

Lender & Investor Technical Advisory

Independent engineer reviews, dispatch assumption validation, degradation modeling, and bankability assessment for project finance. We speak both the technical language and the financial language.

Engagement Sprints

Scoped, time-bound engagements with defined deliverables, priced per sprint.

Bid Stage

2–3 weeks

Portfolio Connectivity & Asset Placement

Multi-criteria optimization for asset placement and connectivity allocation across complex FDRE, RTC, and hybrid portfolios. Preferred interconnection strategy, congestion and curtailment impact, capex vs evacuation trade-offs, and battery value under constrained evacuation — delivered with MESH-T, our portfolio IRR optimizer, as a scoped advisory engagement.

2–4 weeks

Bid Advisory

FDRE/RTC bid-stage support — optimal RE-BESS sizing, connectivity mapping, degradation-adjusted dispatch assumptions, and non-linear equity IRR modeling to maximize competitiveness.

Contract & Build

2–4 weeks

Technical Contract Closure Sprint

End-to-end technical review, red-flag identification, and clause-level negotiation support to get contracts signed with risk mitigated.

2–4 weeks

Design Review

SLD to layout to BOM — independent review of BESS system design, protection philosophy, thermal architecture, and fire safety.

2–3 weeks

EMS Evaluation & Selection

Independent benchmarking of EMS platforms against your commercial strategy. Feature-gap analysis, cost-value assessment, and vendor shortlisting, with no EMS vendor affiliation.

1 week

Thermal Modelling

DCIR-derived thermal model calibrated to site-specific ambient profiles. Cooling system adequacy assessment and thermal headroom analysis.

1 week

Certifications & Compliance Assessment

Gap analysis against IEC 62933-5-1/5-2, UL 9540A, IS 16270 and applicable Indian grid codes. Lab report cross-verification.

1–2 weeks

Factory Acceptance Testing

FAT protocol design and witness testing per IEC 62933-5-2 and 5-1 frameworks, including hardware-in-the-loop verification of the BMS–PCS–EMS integration before energisation. Cross-laboratory certification validation. We've caught scope gaps that would have shipped to site.

1–2 weeks

DSM Controller Logic Specification

Custom DSM logic aligned to your commercial strategy rather than the EMS vendor's default logic. Penalty avoidance, ramp-rate compliance, and scheduling accuracy.

Operate

2 weeks

Trial Run Support

On-site or remote support during trial operations. Performance benchmarking, punch-list tracking, and commissioning sign-off readiness.

2–3 weeks

Post-Commissioning Performance Audit

Independent RTE verification, capacity fade benchmarking against OEM curves, thermal performance vs design assumptions. Identifies revenue leakage before it compounds.

As needed

Dispute Resolution & Technical Expert

Independent technical expert for developer-vendor disputes. Documentation review, root cause analysis, and expert opinion grounded in hands-on commissioning experience.

1 week

BESS Augmentation Planning

When capacity drops below warranty thresholds — optimal augmentation timing, technology selection, and revenue trade-off modeling. On the contract side: integration-support obligations, config-export rights, and non-obstruction clauses that keep third-party augmentation possible. Plan early, save significantly.

Module-specific

Training

Customized modules for IPPs, OEM teams, O&M teams, trading desks, or project management. Covers BESS operations, IEX market mechanics, dispatch strategy, safety protocols — and helps OEM teams understand Indian market requirements and developer expectations.

Who We Serve

Built for India's Grid

Primary

FDRE / Hybrid IPPs

Independent power producers with firm delivery renewable energy contracts. Your bid-stage equity IRR assumes optimal dispatch — PRISM delivers it within the PPA and warranty constraints.

FDRE ContractsHybrid RE + BESSMerchant Operations
Expansion

Tier 2 Hyperscalers

Data center operators scaling capacity with hybrid RE PPAs to meet sustainability and RPO commitments. The 24/7 clean energy matching problem is structurally identical to FDRE dispatch — same optimization, different buyer.

24/7 Clean EnergyHybrid RE PPAsRPO Compliance
Expansion

C&I Supply

Developers structuring group captive and open-access supply, and the manufacturers and commercial operators they serve. COMPASS solves both sides — generator IRR held at target, consumer savings maximized across load profiles — before the PPA is signed.

Group CaptiveOpen AccessMulti-Consumer Portfolios
Ecosystem

Lenders & Investors

Project finance institutions and equity investors needing independent technical diligence on BESS and hybrid assets. Dispatch assumption validation, degradation modeling, and bankability assessment from someone who's built and operated these systems.

Project FinanceTechnical DDIE Reviews

Knowledge Series — Starting November 2026

Technical Webinars

Monthly sessions on BESS operations, dispatch strategy, and hybrid asset management — 30 minutes each, built on real project and market data. Last Thursday of every month.

Live on YouTube. Register to get notified.

Get in Touch

Let's Talk

Whether you're optimizing dispatch, sizing a bid, or evaluating vendors — we'd like to hear from you.

or write to info@elarispower.com